Commisioning of Bijlander bicycle highway

Thursday, August 24, 2017

Thursday, August 24, 2017, the final round was done in connection with the comissioning of the environmental works linked to the cable works. Elia provides a new 150kV substation in Ypres from which a new 150 / 15kV transformation station in Neerwaasten is fed. For this, a new 150kV cable is set between Ypres and Bas Warneton.
 
We renewed the road over a total length of almost 18 km. Restored roadsides in its original state and with respect for local biodiversity. But in particular, the Bijlander road wich is  managed by W & Z and in conjunction with the city of Ypres and ANB as a cycling highway from Ieper to Heuvelland. With the beautiful open frame of landscapes and views of the Westhoek.
 
We are proud to have cooperated and thank all parties for the fine cooperation